AN UPDATE FROM HUMMINGBIRD ON KOUROUSSA GOLD MINE , GUINEA
PROJECTS AND EXPLORATION • advancing , notably including progress with both the co-lending bank and the local equity-capital investors .
A positive development is that recent regulatory changes have facilitated the improvement to the equity funding structure which has lowered overall finance costs . The regulatory changes of note were the foreign exchange exemptions , the increase in the maximum permissible ratio of debt to equity from 70:30 to 80:20 and the deeming as foreign direct investment the re-investment of the local currency ( Ethiopian BIRR ) retained earnings of multi-national corporations ( MNC ) into new business sectors .
Within the development capital budget of USD320-million , USD100-million was to be provided through the issuance of two types of Equity Risk Notes ( ERN ), one type for MNC ’ s with no operations in Ethiopia and another lower-cost ERN for those with accumulated retained earnings in Ethiopian operations . The company reported that it can now focus on the lower-cost ERN - fixed at 12 % per annum . These notes remain repayable in cash from operations or , as a fall-back , in KEFI equity ( at KEFI ’ s election ), convertible in year 4 ( being year 2 of full production ) at the then prevailing KEFI share price .
The company confirmed a longstanding and large MNC investor in the ERN has now received initial board approvals . All syndicate members have agreed a schedule for all remaining pre-launch tasks including their respective formal approvals ahead of full financial close mid-2024 .
Harry Anagnostaras-Adams , KEFI executive chairman , commented : “ I am delighted to report the initial board approval of a major local equity-capital provider . And it is especially pleasing that the instrument designed for this transaction , the Equity Risk Note , has been streamlined under the lower-cost approach . Our modelling and production profile for this high-grade open pit gold mine , based on a gold price of USD1.864 / oz ( versus current spot of USD2.170 / oz ), shows sufficient cash will have been generated at the proposed time of repayment to repay these ERN in cash at the time they fall due .
“ When combined with the credit committee approved USD95- million debt from lead bank Eastern and Southern Trade and Development Bank ( TDB ) and the Ethiopian Federal and Regional Governments ’ USD20-million commitment , with the potential to increase to USD40-million , this accounts for USD215-million to USD235-million .
“ I can also advise the company has received confirmation from the co-lender Africa Finance Corporation ( AFC ) that its approval processes are underway and progressing well for its-intended USD95-million investment , which would provide the balance of the required funding for project launch .
“ All syndicate members are supportive and are working to ensure final documentation is entered into by mid-2024 to enable full project launch and drawdown of funds . I look forward to providing further updates as appropriate .”
Source Supplied by KEFI Gold and Copper
Image by PNG Tree
AN UPDATE FROM HUMMINGBIRD ON KOUROUSSA GOLD MINE , GUINEA
Location : Guinea Phase : Processing Resource : Gold
On 28 March 2023 , Hummingbird ( AIM : HUM ) provided an update regarding the situation surrounding the Kouroussa Gold Mine in Guinea , following the suspension of mining activities by Corica Mining Services on 17 March 2024 .
The company says it has been actively seeking to address the ongoing situation by engaging in discussions with Corica , alternative and additional mining contractors , suppliers and its primary lender , Coris Bank International .
At the time of the update , the company ’ s senior management team met with a number of these key stakeholders in West Africa . The objective of these discussions was to restart mining operations at Kouroussa as soon as possible and outline a path towards achieving sustainable commercial production levels . Discussions remain ongoing .
As a consequence of the current significantly reduced mining activity , achieving commercial production will be delayed beyond the Q1 2024 target , until full mining capacity is restored onsite . In the meantime , the supporting mining contractor continues to operate , with the processing plant processing this ore , together with stockpiled material . Resolution to the current situation will allow the upcoming blast to proceed , which is expected to provide access to higher-grade ore necessary to achieve commercial production .
Discussions are focused on various scenarios and initiatives , with the company confident of reaching a constructive resolution in the near term . Further updates will be provided . •
Source Supplied by Hummingbird Resources
Achieving commercial production will be delayed .