African Mining July 2026 | Página 14

• PROJECTS AND EXPLORATION
The milestones include the completion of construction of the 4-million-tonne-per annum( Mtpa) Shaft 3, the breaking of ground for the Phase 2 concentrator site and the commencement of widening of Shaft 2. The project milestones are a major advancement for the Phase 2 expansion and the future Phase 3 expansion, reflecting a steady progress in the phased development of Platreef, which is expected to play a major role in the future supply of platinum group metals( PGMs) and critical minerals.
Located in Mokopane, South Africa, Platreef is distinguished by its thick, high-grade orebody and its suitability for large-scale mechanised mining – a combination that underpins both its operational efficiency and long-term economic potential.
The latest developments signal Ivanhoe Mines’ continued focus on disciplined execution, capital efficiency and de-risked project advancement as the company moves closer to bringing the project into production.
Even if commodity prices weren ' t at an all-time high, it would still be a sustainable project in a depressed cost environment.
Speaking to African Mining, incorporating Mining Mirror at this year’ s PGMs Industry Day, Ivanhoe Mines’ president and CEO, Marna Cloete, provided additional context on why Platreef continues to stand out as a globally competitive development.
According to Cloete, the project’ s fundamental strength lies in its orebody and cost position.“ Platreef sits at the bottom of the cash cost curve. It is a bulk, mechanised mine with a reef thickness of around 25m at grades comparable to what you see in Rustenburg. That makes it highly amenable to efficient, cost-effective mining,” she explained.“ If you run the numbers, it delivers strong margins, even in a lower commodity price environment, which makes it a sustainable, investable project.”
( DRC), where we have built a large-scale copper mine and the same philosophy applies here,” she said.
“ That is why projects are developed in phases – to test what works, optimise what does not and then scale with confidence.”
The phased approach adopted at Platreef is central to Ivanhoe Mines’ broader project development strategy, allowing for technical validation, operational optimisation and capital discipline before full-scale ramp-up.
An on-site ceremony was held at the mine to celebrate this milestone, attended by Cloete, senior management from the company and Ivanplats, as well as representatives from Ivanplats’ shareholders, Japan Organisation for Metals and Energy Security( JOGMEC), and ITOCHU Corporation and the broad-based black equity empowerment( B-BBEE) group.
Ivanhoe Mines founder and co-chairperson Robert Friedland said the mine was not a typical South African precious metals mine, scratching at narrow, one-metre-thick seams.“ The Platreef Mine is a once-in-a-generation geological wonder, a discovery so vast that it will be producing precious metals for generations to come. The flat-lying orebody is approximately twenty-five times thicker than our industry incumbents, averaging 26m of continuous mineralisation thickness, which means scale, which means mechanisation, and mechanisation means lower costs and safer operations.”
“ We are ramping up the mine at a time when metal prices are rising. Scarcity is real and the demand is relentless. Platinum, palladium, rhodium, copper and nickel are identified by countries all around the globe as critical minerals and are therefore strategic to the agenda of many of the world’ s developed and developing economies,” added Friedland.
Reference: https:// www. ivanhoemines. com / wp-content / uploads / 20260423-Platreef-Shaft- 3-Complete-VF. pdf
This margin resilience is particularly notable in the current PGM market, where cost pressures have placed many operations under strain.“ The ore body speaks for itself. Even if commodity prices weren ' t at an all-time high, it would still be a sustainable project in a depressed cost environment.”
Beyond geology and cost competitiveness, execution capability remains a defining factor as the project progresses through its development phases.“ You need a seasoned execution team, strong engineering studies and a clear understanding of risk. We have applied this approach in the Democratic Republic of Congo
About: On 18 February 2025, two independent studies were completed on the three-phase development of the Platreef Mine. This included an updated Feasibility Study on the Phase 2 expansion to 4.1Mtpa of processing capacity, as well as a Preliminary Economic Assessment covering a new Phase 3 expansion to 10.7Mtpa of processing capacity. The excellent results from both studies reinforce the multi-generational Platreef Mine ' s industryleading margins.
12 • African Mining • July 2026 www. africanmining. co. za