TKGM FORMALLY LAUNCHES TULU KAPI GOLD PROJECT
PROJECTS AND EXPLORATION •
Supplied by Walkabout Resources Limited
Operations Mining operations have recommenced in accordance with the three-year mine plan despite load and haul operations having been affected by recent extreme weather conditions since January . Mining performance during dry periods demonstrate ample capacity to compensate for restricted operations during periods of high rainfall .
The ROM high-grade stockpiles ( refer table 1 ) have increased by approximately 15 000 tonnes of “ free-dig ” graphite ore bringing the total ore stockpile to ~ 34 000 tonnes which is more than an entire month ’ s plant throughput at nameplate capacity .
Table 1 : ROM High-grade stockpiles at Lindi Jumbo Graphite Mine as at the end of April 2024 .
Operational priorities Current short-term priorities of Lindi Jumbo include :
• Final commissioning and functional handover of the plant under the EPC contract ;
• Progressively increasing throughput while increasing process consistency , ensuring product quality / grade and maximising flake size retention as per the production ramp-up schedule ;
• Dispatching of final product to Wogen as available ;
• Ramping up production rates to the 40kpta market capacity within 4 months ;
• Targeting nameplate recoveries of > 85 % within 12 months ;
• Looking for opportunities to produce and sell additional quantities of graphite from the > 20 % of built-in excess capacity in the Lindi Jumbo plant .
It is expected to take several weeks to achieve the 48 hours of uninterrupted production at nameplate capacity to have the plant formally commissioned under the EPC Contract . Until that point the plant remains under the control and responsibility of the EPC contractor . Ramp up of the processing plant at Lindi Jumbo will focus on safely and sustainably increasing throughput to the 40kpta market capacity through optimising plant availability and utilisation while at the same time gathering and documenting essential processing and metallurgical information through the various stages of the processing circuit .
Once throughput levels are sustained , and using the baseline data collected during the previous phases , the focus will be on grade and flake size distribution to ensure that the plant performs as closely as possible to its design parameters . With the goal of being the producer of choice for highgrade , high-quality , large-flake graphite concentrate Lindi Jumbo will need to ensure that all its products meet the specification requirements for regular customers . At the very high reserve grade of 17.9 % TGC reserve grade ( including significant zones of > 25 % TGC ), Lindi Jumbo has the luxury to leave the pursuit of higher recoveries to last after throughput , quality and flake size targets are achieved , the metallurgical team at Lindi Jumbo will seek to tweak the processes to improve recoveries without sacrificing other product objectives .
Source : Supplied by Walkabout Resources Limited , as at 2 May 2024 .

TKGM FORMALLY LAUNCHES TULU KAPI GOLD PROJECT

Location : Ethiopia | Phase : Exploration | Resource : Gold
On 20 May 2024 , KEFI ( AIM : KEFI ), the gold and copper exploration and development company focused on the Arabian-Nubian Shield with a pipeline of projects in the Federal Democratic Republic of Ethiopia , and the Kingdom of Saudi Arabia , advised that the board of Tulu Kapi Gold Mines ( TKGM ) has formally launched the project .
The TKGM board includes representatives from both KEFI and the Ethiopian Federal and Oromia Regional Governments . This decision to launch Tulu Kapi follows deployment of dedicated site policing and the conditional confirmations that quickly ensued from all members of the project ’ s finance syndicate .
Harry Anagnostaras-Adams , KEFI ’ s executive chair commented , “ Our launch timing is fortuitously coinciding
Image by Freepik . com with the improved conditions in Ethiopia and all-time high gold prices . Tulu Kapi ’ s high grade and high process recovery , combined with our project design , has resulted in a robust set of economics for long-term operations which should support further exploration and development along with good opportunities to continue supporting local social development projects such as the already provided local school and water supply . The returns for the capital investors and lenders are attractive and the recent exemptions from exchange controls has rendered the Ethiopian mining investment climate internationally competitive .
“ We can now proceed to safely complete our Early Works on schedule and satisfy all conditions precedent to drawdown full project finance as outlined , thus enabling the Major Works to commence from October 2024 . This deliberately sequenced and disciplined approach is commensurate with being a first mover adhering to the highest performance standards in respect of safety , social , environmental , technical and other aspects . We are determined to ensure that Tulu Kapi preserves its standing as a showcase project for an important new business sector for Ethiopia .
“ We greatly appreciate the support of the community and all local and international stakeholders .”
Early Works until September 2024 include :
• Completion of preparation for community resettlement ;
• Detailed engineering for procurement ;
• Community consultations on social development plans ; and
• Recruitment and other organisational development . •
Source : supplied by KEFI Gold and Copper plc