African Mining April 2020 | Page 15

MINE EXCURSION  the team explains that the top part of the structure which has remained above the water level, has deteriorated more rapidly as a result of being exposed to oxygen. According to Shamu, closer inspection of the steel members (above the water), has revealed that the main structural steel members are still 9mm thick, despite the wear and tear, which is still above the specs for a framework of this size and strength. The original steel installed by Anglovaal was 10mm in diameter. “A shaft of this size needs beams of only 7mm for the duties we plan for. Besides, we are not intending to overwork the shaft. In the Anglovaal days the mine was hauling out 250 000 tonnes of ore per month (tpm); we will only be carrying 200 000tpm with two skips, each weighing 22 tonnes, so we will be well below the maximum capacity,” says Shamu. He adds that Orion has made provision for 30% of the shaft’s steel to be removed and replaced. Access to a world-class VMS deposit Errol Smart, managing director and CEO of Orion says that initially they felt the water would be too murky to get a clear view all the way to the bottom of the shaft. “But at the moment (at the time of writing in early February 2020) we are at 758m below the water surface with the camera and we have visual confirmation that there are no skips or cages in the shaft, which was our other initial concern, says Smart. So, is there a plan B in case the steel structure and headgear are found to be unsafe and cannot be used? Shamu explains that it will obviously result in a drop in margins, but that it would have to be almost a complete collapse to render the shaft unusable. “In the worst-case scenario, we still have the decline, which means we won’t be working optimally, but the project will still be viable,” says Shamu. Below 1025 level, underneath the bottom level of the historic mine workings, Orion intends accessing what Van Schalkwyk regards as “world class VMS copper and zinc deposit of 30.49 million tonnes (Mt) at 1.2% copper and 3.7% zinc.” The ore body dips steeply and remains open to strike but flattens out considerably at depth, which is why Anglovaal packed up and left. They needed to recapitalise to go deeper and just couldn’t do it, exactly why Orion needs to raise an additional USD400-million in funding before work can continue. The portal decline access at Prieska is still in immaculate condition. The bulk of Orion’s new footprint will start below the 957m level. That is where they will construct new declines. Anglovaal made a start in the eighties and blasted an initial trail starting at 1025m below surface. They used small trucks and Load Haul Dumpers (LHDs), which wasn’t very efficient, and they just couldn’t keep up with development. “We will use more efficient methods of lateral development which will allow us to extract more ore and build an excellent business case of mining the rich, deeper deposit, “says Shamu. Mining the ore To get the ore out, Anglovaal utilised extremely intensive mining methods. They used 3.4m by 3.4m drives, 2.4km long. At that time, they obviously didn’t use remotely-operated equipment and used crosscuts instead of open stopes, in the process leaving fantastically sound hanging and footwalls. Thereafter they put in long holes and had three levels to work from and dropped the ore down ore passes to a rail system at the bottom level. At the peak of mining, Anglovaal deployed up to 42 LHD’s at any one time in the mine. When Anglovaal left in 1991, they left all the tunnels and shafts intact. www. africanmining.co.za African Mining Publication Thus, the mining method then was extremely development- intensive. Orion, on the other hand, will automate as much of African Mining African Mining  April 2020  13