Johnsville construction update presented Chuck Holden, chief operations officer, and Dr. Mary Wolverton, associate superintendent for elementary schools, presented an update to the board on the bid rescision for the addition on Johnsville Elementary School. At the last regular meeting, the board awarded the bid to Jorgenson Construction. But another construction company challenged the bid, citing a new Minnesota state statute requiring contractors to get sworn statements for the work from their subcontractors, which wasn’t done by Jorgenson, Holden said. As a result, district legal counsel recommended the district re-bid the project. The bid was reopened March 12 and will wrap up March 27, Holden said. But the re-bid process is creating a six-week construction delay, Holden said. As a result, the proposed heating, ventilation and air cond