Problem 7S-4
A job is known to have a learning percentage equal to 82. If the first unit had a completion time of
20 hours
Problem 7S-11
The first unit of a job took 40 hours to complete. The work has a learning percentage of 88. The
manager wants time estimates for units 2, 3, 4, and 5. Develop those time estimates. (Do not
round intermediate calculations. Round your final answers to 2 decimal
places.)