1. Problem 17-13
Here is a list of activity times for a project as well as crashing costs for its activities. Determine
which activities should be crashed and the total cost of crashing if the goal is to shorten the
project by three weeks as cheaply as possible. (Omit the "$" sign in your response.)
Activity
Duration
First Crash
Second Crash
(weeks)
1-2
5
$8
$10
2-4
6
7
9
4-7
3
14
15