1. Problem 16-8
The following table shows orders to be processed at a machine shop as of 8:00 a.m. Monday.
The jobs have different operations they must go through. Processing times are in days. Jobs
are listed in order of arrival.
Job
Processin
Due
Remaining
g Time
Date
Number of
(Days)
(Days)
Operations
A
8
20
2
B
10
18
4
C
5
25
5