PROJECT UPDATES By Brett Marlin Pinnacle Park We are really close to finishing phase 1 and expect it to be complete by the beginning of June 2020. Phase 2 should be complete by the end of July. This excludes all the tenant fit-outs such as partitioning and flooring which will be done in conjunction with the tenants. Boiteko Junction refurbishment The design of the extension to the centre is almost complete and we are hoping to have the tenants secured, building approval and construction works tendered for a start by October 2020. Sesigo Mews We have revised the project schedule based on us being able to start working on 25 May. Our plan is to have the project complete by the end of November and to give occupation to the purchasers during December 2020. Setlhoa showrooms We would have already handed over the first set of units, but we now plan to hand over the first six units at the end of June and the balance of eleven units at the end of August. 6 ISSUE 42 - JUNE 2020