PROJECT UPDATES
Motswedi Place
By Roy Mapharing
We are progressing well at Motswedi Place . The building platforms for eight blocks were completed in May , with the use of the raft foundation system . We had to make sure that all the ground services and reinforcement were carefully coordinated before casting the concrete slab . The sales on Phase 1 were an immediate success . The Phase 2 building contract has been awarded to the main contractor . Sales for the development have been impressive and are ongoing .
Barloworld Equipment Botswana
By Mmika Selei
In the last project update we said that we hope the contractor will start on site before the end of the first half of 2022 . The tender adjudication has been completed and the recommendation has been made to the client . Unfortunately , there were compliance issues that had to be met from the client ’ s side before the works can be awarded . The client is currently working on fulfilling these requirements and once completed we will be instructed accordingly to proceed .
Prime Plaza II By Tapiwa Modise
Red East Construction is ahead of program with the basement level 2 structure almost complete and only the surface bed remains to be finalised . The basement level 1 structure covering the slab , retaining walls , columns , lift area , staircase and ramps are all finished and work has started on the ground floor structure .
8
ISSUE 51 - SEPTEMBER 2022