TIMELINE Floor Plans Site Plans Budget Review Exterior Massing Initial Renderings S C H E M AT I C DESIGN Summer 2017 INTERLACHEN COUNTRY CLUB DESIGN DEVELOPMENT Initial Specifications (Finishes, Furniture & Materials) Cost Estimating Approval of 3D Design Summer / Fall 2017 Building Permit Final Technical Drawings & Specs Final Pricing CONSTRUCTION D O C U M E N TA T I O N Fall 2017 / Winter 2018 CONSTRUCTION KICKOFF Construction Kickoff Site Meetings w/ Contractor Shop Submittals Winter 2018 CONSTRUCTION SCHEDULE Pool Locker Rooms - Summer 2018 Clubhouse Main Level - Fall 2018 Clubhouse Lower Level - Spring 2019 Tennis - Winter 2018 Golf Performance Center - Winter 2018 FACILITIES IMPROVEMENT PLAN | TIMELINE | 15